PATTAYA, Thailand – Pattaya is moving ahead with a major four-phase drainage project worth more than 1.8 billion baht for its first two phases, aiming to reduce flooding in key commercial areas, Soi Buakhao and Wat Chai Mongkhol. Construction is expected to begin in early 2027. Nattaphong Saenthaweesuk, director of Pattaya’s drainage and flood prevention system management division, who is currently acting as director of the city’s Sanitation Engineering Office, outlined the project at the first 2026 executive policy meeting on Pattaya’s development plans.
Designed by the Department of Public Works and Town and Country Planning, the four-phase project will improve drainage capacity across the city, directing stormwater towards South Pattaya Canal before discharging it into the sea. Phase 1 will collect water from Pattaya Third Road and surrounding streets and sois before channeling it into South Pattaya Canal. The estimated budget is 970 million baht.
Phase 2, with an estimated budget of 870 million baht, will install drainage infrastructure to collect water from Sukhumvit Road towards Pattaya Third Road and discharge it into the same canal.
The first two phases are scheduled to take three years, beginning in 2027 and targeting completion in 2029. The combined budget is approximately 1.84 billion baht.
Phase 3 will cover an area operated by the Provincial Electricity Authority, using a 3.6-metre-diameter drainage tunnel to carry water from Soi 4 near the railway line towards South Pattaya Canal.
Phase 4 will address flooding around Khlong Noi, diverting water from areas along the railway corridor into South Pattaya Canal. Pattaya plans to seek funding for the final two phases in 2028, with completion targeted for 2030.
The construction method will involve excavation shafts measuring approximately 10 to 12 meters wide, followed by underground tunneling. The work could affect traffic in some locations, so the city will coordinate with contractors and relevant agencies on measures such as designated construction zones, detours and possible night-time work to minimize disruption.
Once all four phases are completed, the drainage network is expected to improve flood management around the Provincial Electricity Authority area, Khlong Noi, the Sukhumvit Road corridor, Soi Buakhao, Wat Chai Mongkhol and communities surrounding South Pattaya Canal.
Pattaya aims to begin construction in early 2027 after the contractor selection process is completed.