PATTAYA, Thailand – The Electricity Generating Authority of Thailand (EGAT) has announced a temporary traffic closure on Motorway Route No. 7 (Bangkok–Chonburi) near kilometer marker 53+530 in Khao Din Subdistrict, Bang Pakong District, Chachoengsao Province, close to the Bang Pakong Power Plant.
The closure is required to allow workers to install high-voltage transmission lines between poles 1D and 1E crossing the motorway. Traffic in both inbound and outbound directions will be halted briefly on Tuesday, November 11, during 10:00–10:10 AM and again 11:00–11:10 AM.
EGAT apologized for any inconvenience caused and requested motorists to follow traffic signs, detour instructions, and road safety regulations during the operation.
For more information or to report issues, contact Phatphoom Phumsano, Project Supervisor, at 098-935-3895, or call the EGAT hotline at 1416.