Thailand’s northern railway to China nears 74% completion, targets 2028 opening

0
100
Construction of Thailand’s Den Chai–Chiang Rai–Chiang Khong railway has reached 74.076%, with the 323-kilometre route expected to open in 2028.

BANGKOK, Thailand – Northern rail link to China nears 74% completion, targets 2028 opening Thailand’s 323-kilometre Den Chai–Chiang Rai–Chiang Khong double-track railway is nearly 74.1% complete, with the State Railway of Thailand (SRT) targeting completion in January 2028, paving the way for improved passenger travel, freight transport and cross-border trade with Laos and southern China. The 85,345-million-baht project, covering construction and land expropriation, will connect four northern provinces, Phrae, Lampang, Phayao and Chiang Rai, linking Den Chai in Phrae with Chiang Khong near the Thai-Lao border.

The railway will pass through 59 subdistricts and 17 districts over approximately 323.1 kilometres, providing a new transport corridor connecting northern Thailand with the Chiang Khong border crossing, the Fourth Thai-Lao Friendship Bridge and onward routes through Laos towards Kunming in southern China. The route will comprise 26 stations, from Den Chai through Phrae, Lampang, Phayao and Chiang Rai to Chiang Khong, expanding passenger and freight connectivity across the northern region.

Construction includes ground-level tracks, elevated sections, bridges and four railway tunnels. These include the 1.175-kilometre Song Tunnel, the 6.24-kilometre Ngao Tunnel, the 2.7-kilometre Mae Ka Tunnel and the 3.4-kilometre Doi Luang Tunnel. Railway crossings are also being addressed through bridges, underpasses and elevated structures at 254 road-rail crossing points.

Construction progress reaches 74.076%
As of October 2026, construction across the three contracts had reached 74.076%, approximately 2.946 percentage points behind the overall schedule.

Contract 1, covering the 103.7-kilometre Den Chai–Ngao section with a budget of 26,560 million baht, is being undertaken by a joint venture involving Italian-Thai Development Plc and Nawarat Patanakarn Plc. Progress reached 75.898%, approximately 8.579 percentage points behind schedule. The section is scheduled for completion on January 14, 2028. The 6,215-metre Ngao Tunnel, the longest railway tunnel in Thailand, has recently achieved breakthrough.

Contract 2, covering the 132-kilometre Ngao–Chiang Rai section with a budget of 26,890 million baht, is being constructed by a consortium involving Ch. Karnchang Plc, Sino-Thai Engineering and Construction Plc and Buriram Pana Sit Co. Progress reached 75.124%, slightly ahead of schedule by 0.079 percentage points.

Contract 3, covering the 87-kilometre Chiang Rai–Chiang Khong section with a budget of 19,385 million baht, is being undertaken by Ch. Karnchang Plc, Sino-Thai Engineering and Construction Plc and Chiang Mai Construction Co. Progress reached 70.125%, ahead of schedule by 0.576 percentage points.
Travel time, trade and tourism benefits
SRT Governor Anan Phonimdaeng said the new double-track railway is expected to reduce journey times by approximately one hour to one hour and 30 minutes compared with travelling by car.

The railway is expected to support tourism, trade and investment, generate income for communities along the route and reduce freight transportation costs. It will also provide businesses with greater access to rail transport for agricultural products, industrial goods and international cargo.

The connection to Chiang Khong is expected to strengthen northern Thailand’s role in cross-border trade, creating additional opportunities for exports, investment and international transport links through Laos towards China.

The route’s scenic landscape, featuring mountain ranges, bridges and tunnels, is also expected to attract Thai and international tourists, adding a tourism dimension to the railway’s transport and economic benefits. The SRT says it will accelerate the remaining work across all three contracts to meet the 2028 completion target.