Pattaya Mail Web

 

Property - Real Estate
HEADLINES [click on headline to view story]: 

Property update: Northpoint Condominium


Send your property related articles to: E-mail: [email protected]

Property update: Northpoint Condominium

With Northpoint now a landmark on the Pattaya skyline, construction through June continued to make strong progress.

The Northpoint Towers stand tall over the Wong Amat coastline.
Site clearance and piling works to the “Zone A” landscape area between the front of Tower A and the Wong-Amat Beachfront are still ongoing. The pile casting for the main pools at the beachfront are now complete and reinforced concrete slabs are being cast.
Mechanical, electrical and plumbing first fix installations have progressed towards the penthouse levels of both towers, and the second fix installations are progressing significantly at both towers to follow. The electrical busduct installations are ongoing.
Permanent power and water supply applications have been progressed and are expected to be connected at site according to programme. The passenger lift installations are ongoing with designated lifts having now been tested, commissioned, protected and handed over to the Main Contractor for temporary use during the remaining works. Two of four external temporary passenger hoists have been de-commissioned and removed from site accordingly.

Swimming pools structural work in process.
The transformer building reinforced concrete roof slab has been cast and associated waterproofing works completed.
Externally, the towers walls surface preparation and Lanko skim coat application process is ongoing and the textured and flat paint decorative applications to the façade are being progressed at both towers. Internal block work walls and plastering have been substantially completed, followed closely by installation of aluminium and glazing installations to the facade and balconies of the buildings.
Imported floor and wall tiling installation works remain ongoing and have significantly advanced at both towers, internal ceiling installations have progressed equally, followed closely by kitchen fit-out and appliances installations; built-in wardrobes installations; vanity units, joinery doors and floors, and frameless shower cubicles.
Sanitary ware installations are also making good progress up the building at site with deliveries ongoing to the site commensurate with installation progress.
The main entrance lobby area to both towers are in the process of fit-out works with general lift lobby and corridor area fit-out works also progressing within the towers. (Source Raimon Land)



News | Business | Features | Columns | Mail Bag | Sports | Auto Mania
Our Children | Travel | Our Community | Dining Out & Entertainment
Social Scene | Classifieds | Community Happenings | Books Music Movies
Clubs in Pattaya | Sports Round-Up


E-mail: [email protected]
Pattaya Mail Publishing Co.Ltd.
62/284-286 Thepprasit Road, (Between Soi 6 & 8) Moo 12, Pattaya City
T. Nongprue, A. Banglamung,
Chonburi 20150 Thailand
Tel.66-38 411 240-1, 413 240-1, Fax:66-38 427 596

Copyright © 2004 Pattaya Mail. All rights reserved.
This material may not be published, broadcast, rewritten, or redistributed.

.